Blanket line

Blanket line

2021. main project was building the blanket line. As we have built similar one before, then this time the process went more smoothly. Only hard part was to get automatic components on right time, due to that final delivery was late 2 months. This time we tested the whole line in our factory, because customer wanted to see machines runningbefore delivery. Assembling time was 1700 working hours. Machines were delivered to Asia, thanks to that we got experience how to load big and heavy machineries to the containers.